Setting up an establishment is much more than putting a
signboard up and waiting for customers to walk in. It requires negotiating a
favourable plot or shed purchase, organising for proper construction of
building, design of interiors and finding good deals for equipment and
machinery.
|
Construction
of Building
|
|
Once an industrial plot for the unit is secured, then the next
job is that of finding a suitable architect. Design of factory building has
to be in consonance with the type of industry and have an appropriate plant
layout.
|
|
An architect's estimate of building construction is essential
for loan applications. Further, architect's certificate for money spent on
building is needed for disbursement of loan.
|
Getting
the Utility Connections
|
|
Among the utilities of prime importance are power and water. In
many cases getting power connection causes delay in setting up of plant.
Therefore it is imperative to commence work on these aspects with diligent
follow up. Power connections are generally of either LT (Low Tension) or HT
(High-tension) type. If connected load is upto 75 HP, LT connection is
provided. For connected loads of 130 HP or higher only HT connection is
provided.
|
|
A formal application needs to be made in a specified form to the
state electricity board. An electrical inspector is deputed for evaluation of
application to factory site, after which the load is sanctioned. In areas of
power shortage, it is advisable to augment the power supply with a captive
generating set.
|
|
|
Water connection is also obtained likewise by applying in
advance in formal forms. The water supply can be augmented by installation of
tubewell.
|
Getting
3M's Right
|
Men
|
|
Projections for manpower and staffing are made in the project
report. However it is necessary to time the induction of manpower in a
planned manner. The engineers and operatives must be available before the
installation of the machinery.
|
Machinery
|
|
Choosing and ordering of right machinery is also of paramount
importance. In many cases technology or process provides us with
specifications which is not provided, then an extensive techno-economic
survey of machinery and equipment available must be carried out.
International trade fairs and engineering fairs are good places to look at
available options. The entrepreneur must also consult experts, dealers /
suppliers as well as users, prior to making a selection of equipment and
machinery. The advice of DIC, MSMEI and NSIC can also be sought.
|
Materials
|
|
Materials procurement and planning are critical to success, of a
start-up with a MSME unit. Inventory management can lead to manageable cash
flow situations; otherwise if too much is ordered too soon considerable
amount of working capital gets locked up. On the other hand, non-availability
may result in production hold-ups, and idle machine and manpower. For
essential imported raw material whose lead-time is large proper planning is
all the more essential.
|